This insight is more than 1 year old
Clean power

Regen's response to NESO's Connections Reform Phase 3 consultation

Date
December 10, 2024

Table Contents

Executive summary

Regen has been closely engaged in the reform of the connections process, drawing on the expertise of its 200 member organisations. We held a working group on the consultation proposals, which was attended by more than 100 members, and discussed the key issues with Energy Minister Michael Shanks and Connections Delivery Board chair Jack Presley-Abbot at the recent Electricity Storage Network annual conference. We have also provided a forum on the details of the reform, to support our members to respond on their own behalf.

Regen is supportive of the process of connections reform. The current processes for connecting to the transmission and distribution networks have led to long timelines to connect and are not fit for purpose for the energy transition. The shift to strategic planning of the energy system also means that reform is required to align connections policy with these plans.

We are grateful for the work put in by NESO, and many in the industry, to developing an entirely new connections process on an accelerated timeline. Our response is focused on how connections reform will impact achieving the CP30 mission and support the GB market to attract the scale and pace of investment in generation and storage projects required.

Key takeaways

The following four areas have seen the greatest degree of consensus from industry:

  • 1

    Clarity and consultation on what technologies are required where. There is a pressing need for NESO to set out its methodology for deriving regional technology pots and to provide industry with a chance to comment on this.

  • 2

    Investment hiatus. To mitigate the risk of this, projects with CfDs and Capacity Market agreements should be exempted.

  • 3

    Competition and interaction with CfDs. Project attrition must be assumed to maintain market competition. A clear process to manage substitution will be needed.

  • 4

    Queue order. Using the date of application for a connection to the grid, whether that was at distribution or transmission level, as the ‘clock start’ date is a fairer way of applying the new queue order to existing projects.

STAY INFORMED

The Dispatch

Sign up to receive our monthly newsletter containing industry insights, our latest research and upcoming events.

Submission successful
Thank you for signing up to The Dispatch.
There was an error submitting the form. Please check the highlighted fields in red.